Kaduna-Kano Rail To Begin Three-Month Trial Run

The federal government is planning a three-month trial run of the Kaduna-Kano railway corridor ahead of its scheduled commissioning in December, with passengers potentially enjoying free rides during the period if President Bola Tinubu approves the proposal.

The trial operation is expected to enable engineers and railway officials to assess the safety, structural integrity and operational readiness of the infrastructure before full commercial services commence.

The Permanent Secretary of the Ministry of Transportation, Engr. Funso Adebiyi, disclosed this during an inspection tour of the railway corridor, adding that the government was considering offering passengers free rides throughout the testing period.

If approved, the arrangement would allow passengers to experience the new rail service while giving the authorities an opportunity to identify and address operational challenges before commercial operations begin.

Adebiyi said concerns raised during an earlier inspection had been addressed by the contractors, particularly those relating to passenger safety, lighting and maintenance.

He disclosed that the toughened glass previously installed in passenger areas had been replaced with laminated glass to minimise the risk of injuries in the event of breakage.

According to him, the lighting system has also been upgraded, with the bulbs expected to have a minimum service life of three years.

Beyond completing the infrastructure, the government is also working to develop local capacity to ensure the railway’s long-term sustainability.
Adebiyi said arrangements were being made to provide maintenance equipment, including man lifts, while Nigerian Railway Corporation (NRC) personnel would undergo intensive training in railway station operations.

He explained that the NRC had been directed to nominate engineers for the training, adding that only those who successfully passed the examinations would be retained for operational responsibilities.

The permanent secretary said he would personally participate in the training and examination process before the NRC eventually takes over the management of the railway system.

In another move to improve accessibility, he confirmed that four lifts had been ordered to assist persons with disabilities in accessing different sections of the terminal.

READ ALSO:

On the outstanding connection between Jaji and Kaduna, Adebiyi explained that security concerns and land requirements had necessitated the construction of a bridge.

He expressed optimism that the bridge, which was already at an advanced stage of construction, would be completed within four to six months.

Its completion is expected to allow the railway to extend fully into Kaduna town, improving connectivity for passengers along the corridor.

The government is also looking beyond the Kaduna-Kano project, with Adebiyi disclosing plans to flag off construction of the Ibadan-Osogbo-Ilorin-Minna railway corridor within the next two months.

He added that the proposed Itakpe-Abuja extension was at an advanced stage, awaiting presidential approval to commence construction.

Meanwhile, the Director-General of the Debt Management Office (DMO), Patience Oniha, said the inspection was part of the agency’s responsibility to assess capital projects financed through government funding.

She noted that the railway could stimulate economic activities beyond passenger transportation, particularly for traders, small-scale entrepreneurs and businesses operating along the corridor.

According to her, improved rail connectivity would create opportunities for businesses and communities by facilitating the movement of people and goods.

Oniha added that proposed infrastructure projects would undergo the necessary appraisal and approval processes before additional funding could be provided.

A representative of the construction firm, CCECC, Mark Xu, assured that the company would sustain efforts to deliver the project ahead of the planned December commissioning.